Haughton Pipeline Project

Investment $280 million for Stage 2
Strategic Purpose A water security initiative supporting the city's Ross River Dam water catchment by providing greater capacity to deliver raw water into the Dam to augment or "top up" water levels during periods of very low rainfall.
Status Stage 2 in construction, Stage 1 complete

Project Overview

The Haughton Pipeline is a major water infrastructure project designed to support Townsville's long-term water security. Jointly funded by Townsville City Council and the Queensland Government, the pipeline will provide raw water into the Ross River Dam to "top up" water levels for the Townsville community and industry during periods of very low rainfall. When complete, the infrastructure will serve our community for at least 50 years.

The project is being delivered in stages. Stage 1 involved duplication and enlargement of the existing Haughton River Pipeline and was completed in 2021.

Stage 2 extends the Stage 1 pipeline from the Haughton River to the Burdekin River and includes additional pipeline sections, pump station infrastructure, control systems and commissioning works required for the system to operate as a complete asset.

Planning on Stage 2 began in 2020 with construction commencing in 2023 and has involved the establishment of a construction corridor of approximately 40 metres in width, along with access roads to support delivery along the 28.5 kilometre alignment.

Where possible, Australian-manufactured materials have been used, including Glass Reinforced Polymer (GRP) and Mild Steel Cement Lined (MSCL) pipes along much of the corridor.

Haughton Pipeline Stage 2 Update

Published: 20 January 2026

Council remains committed to completing and commissioning the Haughton Pipeline. The current pipeline will meet community needs until 2032. The Haughton Pipeline must be fully operational by then, to support Townsville's growth and meet projected water demands.

To date, the approved investment for Stage 2 is $280 million, including $195 million in funding from the Queensland Government and $85 million from Townsville City Council. However, rising construction and materials costs since the COVID-19 pandemic, together with a number of technical challenges - particularly relating to pump station design and delivery - have placed additional pressure on the project budget.

Council is currently working through a Concept Study and Business Case that is scheduled for completion in June 2026 and will provide a more refined design and accurate cost estimate.

Additional funding from all partners will be required in future years to complete and commission the pipeline. Council continues to work with the Queensland Government and Sunwater to complete this significant piece of infrastructure, for Townsville's long-term water security.

Council will continue to provide updates as work progresses.

Frequently Asked Questions

Environmental Approval Documents

Environmental approval documents relating to Council’s projects are available on the Projects – Environmental Approval Documents page.

Media Releases

Queensland Government logo

The Haughton Pipeline Stage 2 Project is being developed with the support of the Queensland Government in association with Townsville City Council.