Wulguru Wastewater Infrastructure Resilience Program
| Investment |
|
|---|---|
| Goal | 2.1.1 Enhance the city's ability to create resilient infrastructure through application for external funding and partnerships. |
| Strategic Purpose | To design and model an upgrade for priority wastewater networks, enhancing resilience during high-volume wet weather events. |
| Status | Completed |
Project Background
As part of the 2021/22 Budget, Townsville City Council delivered the third and final stage of the Southern Suburbs Rising Main (SSRM) project, investing a total of $15.7 million to increase the wastewater system capacity in Wulguru. Works included $5.3 million for the construction of a new wastewater pump station and $10.4 million for a new gravity sewer and rising main.
Following the completion of the SSRM project, Council is further enhanced wastewater resilience along Wright Street, Wulguru. Installing new wastewater infrastructure along the street increased capacity, reducing both the volume and frequency of wastewater overflows during wet weather events.
Project Overview
Council delivered this program of works as two projects: the Wright Street Sewer Upgrade and the Stuart Drive Sewer Upgrade. The Wright Street Sewer Upgrade was delivered first, followed immediately by the Stuart Drive Sewer Upgrade. Both projects were delivered to achieve the intended benefits.
Wright Street Sewer Upgrade
The Wright Street Sewer Upgrade involved constructing a 225 mm nominal diameter pipe along Wright Street, extending from the intersection near Powell Street to the intersection near Stuart Drive. This new pipe redirects wastewater from Glenlyon Drive, Powell and Neelsen Streets, relieving the existing 150 mm pipe that currently services residents along Wright Street. Construction of this sewer is now complete.
Stuart Drive Sewer Upgrade
The Stuart Drive Sewer Upgrade extended a 225 mm pipe under Stuart Drive north within the Townsville Turf Club until it connected with the existing 300 mm trunk gravity sewer at the intersection of Stuart Drive and Edison Street. Construction commenced in June 2026 and was completed in October 2026.
Project Updates
Media Releases
- 02/11/2026 – Getting the basics right: Wulguru wastewater upgrade complete
- 17/06/2026 – Council focuses on basics in 2026–27 Budget
- 10/06/2026 – Wulguru major wastewater works surge ahead
- 20/03/2026 – Wulguru wastewater works kick off
- 27/11/2025 – Works to begin on Wulguru wastewater project early 2026