Wulguru Wastewater Infrastructure Resilience Program

Investment
  • FY2025/26:
    • Wright Street Sewer Upgrade: $2,200,000 *
    • Stuart Drive Sewer Upgrade: $400,000
  • FY 2026/27 Stuart Drive Sewer Upgrade: $4.5 million
Goal 2.1.1 Enhance the city's ability to create resilient infrastructure through application for external funding and partnerships.
Strategic Purpose To design and model an upgrade for priority wastewater networks, enhancing resilience during high-volume wet weather events.
Status Completed

Project Background

As part of the 2021/22 Budget, Townsville City Council delivered the third and final stage of the Southern Suburbs Rising Main (SSRM) project, investing a total of $15.7 million to increase the wastewater system capacity in Wulguru. Works included $5.3 million for the construction of a new wastewater pump station and $10.4 million for a new gravity sewer and rising main.

Following the completion of the SSRM project, Council is further enhanced wastewater resilience along Wright Street, Wulguru. Installing new wastewater infrastructure along the street increased capacity, reducing both the volume and frequency of wastewater overflows during wet weather events.

Project Overview

Council delivered this program of works as two projects: the Wright Street Sewer Upgrade and the Stuart Drive Sewer Upgrade. The Wright Street Sewer Upgrade was delivered first, followed immediately by the Stuart Drive Sewer Upgrade. Both projects were delivered to achieve the intended benefits.

Wright Street Wastewater Infrastructure Resilience Program Timeline

Wright Street Sewer Upgrade

The Wright Street Sewer Upgrade involved constructing a 225 mm nominal diameter pipe along Wright Street, extending from the intersection near Powell Street to the intersection near Stuart Drive. This new pipe redirects wastewater from Glenlyon Drive, Powell and Neelsen Streets, relieving the existing 150 mm pipe that currently services residents along Wright Street. Construction of this sewer is now complete.

Wright Street Sewer Upgrade Map

Stuart Drive Sewer Upgrade

The Stuart Drive Sewer Upgrade extended a 225 mm pipe under Stuart Drive north within the Townsville Turf Club until it connected with the existing 300 mm trunk gravity sewer at the intersection of Stuart Drive and Edison Street. Construction commenced in June 2026 and was completed in October 2026.

Stuart Drive Sewer Main Upgrade Map

Project Updates

Media Releases

Documents

Works Notifications

Queensland Government | Delivering for Queensland
Jointly funded by Townsville City Council and the Queensland Government’s Works for Queensland program.