Wulguru Wastewater Infrastructure Resilience Program

Investment
  • FY2025/26:
    • Wright Street Sewer Upgrade: $2,200,000 *
    • Stuart Drive Sewer Upgrade: $400,000
  • FY 2026/27 Stuart Drive Sewer Upgrade: $4.5 million
Goal2.1.1 Enhance the city's ability to create resilient infrastructure through application for external funding and partnerships.
Strategic PurposeTo design and model an upgrade for priority wastewater networks, enhancing resilience during high-volume wet weather events.
Status
  • Wright Street Sewer Upgrade: Defects Liability.
  • Stuart Drive Sewer Upgrade: Construction.

Project Background

As part of the 2021/22 Budget, Townsville City Council delivered the third and final stage of the Southern Suburbs Rising Main (SSRM) project, investing a total of $15.7 million to increase the wastewater system capacity in Wulguru. Works included $5.3 million for the construction of a new wastewater pump station and $10.4 million for a new gravity sewer and rising main.

Following the completion of the SSRM project, Council is preparing to further enhance wastewater resilience along Wright Street, Wulguru. Installing new wastewater infrastructure along the street will again increase capacity, reducing both the volume and frequency of wastewater overflows during wet weather events.

Project Overview

Council will deliver this program of works as two projects: the Wright Street Sewer Upgrade and the Stuart Drive Sewer Upgrade. The Wright Street Sewer Upgrade will be delivered first, followed immediately by the Stuart Drive Sewer Upgrade. Both projects must be delivered to achieve the intended benefits.

Wright Street Wastewater Infrastructure Resilience Program Timeline

Wright Street Sewer Upgrade

The Wright Street Sewer Upgrade involved constructing a 225 mm nominal diameter pipe along Wright Street, extending from the intersection near Powell Street to the intersection near Stuart Drive. This new pipe redirects wastewater from Glenlyon Drive, Powell and Neelsen Streets, relieving the existing 150 mm pipe that currently services residents along Wright Street. Construction of this sewer is now complete.

Wright Street Sewer Upgrade Map

Stuart Drive Sewer Upgrade

The Stuart Drive Sewer Upgrade will involve extending a 225 mm pipe under Stuart Drive and continuing north within the Townsville Turf Club until it connects with the existing 300 mm trunk gravity sewer at the intersection of Stuart Drive and Edison Street. The design has been completed, and construction will commence in June 2026, with works expected to be completed by October 2026.

Stuart Drive Sewer Main Upgrade Map

Project Updates

Media Releases

Documents

Works Notifications

Queensland Government logo

* Jointly funded by Townsville City Council and the Queensland Government’s Works for Queensland program.