You are here: Home Building, Planning & Projects Works & Road Closures List View
Works & Road Closures List View
Townsville City Council is committed to delivering well-maintained infrastructure and efficient transportation systems, with over $400 million being invested in roads and transport management, open spaces, water, and wastewater management this financial year.
This page contains works and road closures currently underway or planned in a screen reader friendly list. To view the interactive map version, visit Works & Road Closures.
For State Government road works and closures, visit Queensland Government Traffic and Travel Information.
Disclaimer: Information should be used as a guide only. Dates and times relating to the works are estimates and may be impacted by weather and project conditions.
Drainage
Date published: Thursday 5 March 2026
Work boundaries: Winifred Street, Mundingburra
Estimated start: Monday 16 March 2026
Expected duration: Four (4) months
Normal work hours: 6am to 6pm Monday to Saturday
Council is continuing flooding and drainage improvements along Winifred Street. With the first and the preloading works along the Ross River riverbank now complete, the project is progressing to the second stage, which includes drainage and roadworks at the Brownhill Street and Winifred Street intersection.
This project is part of Council’s stormwater Capital Works program, designed to address and improve drainage across Council’s networks, and raise the quality of life for residents.
As part of this project, Council will:
- install six additional stormwater inlets around the intersection
- reconstruct the kerb and channel to improve stormwater flow
- construct an additional inlet within the Ross River riverbank
- install underground stormwater pipes
- replace road pavement with new asphalt.
If you live in or are travelling through the area, you may experience:
- diversion of shared path around the construction site
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including road closures, detours, minor traffic delays and reduced speed limits.
Council advises that due to the nature of these works, a road closure will be in place, with clearly signed detours throughout works.

Environmental Restoration
Date published: Thursday 12 March 2026
Work boundaries: Ross River between Mizuno View and Riverwood Drive, Oonoonba
Estimated start: Monday 16 March 2026
Expected duration: Four (4) weeks
Normal work hours: 6am to 6pm Monday to Saturday
Council is undertaking riverbank stabilisation works along the Ross River, in the vicinity of Wes Barrett Park between Mizuno View and Riverwood Drive, Oonoonba.
This project is part of Council’s ongoing commitment to environmental management, which has identified the need to mitigate the effects of recent weather events and enhance the resilience of Ross River.
These works complement earlier stabilisation works completed in the nearby area and will address the existing riverbank erosion cost effectively, with minimal impact to residents.
As part of this project, Council will:
- install stabilising elements
- fill localised erosion scours
- revegetate the area using local native estuarine species.
If you live near or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- footpath closures
- increased levels of dust, noise, vibrations and occasional odour.

Assistance provided through the jointly funded Commonwealth-state Disaster Recovery Funding Arrangements and the Australian Government’s Reef Guardian Council – Activating Local Councils’ Reef Action Plans grant program.
Date published: Tuesday 24 February 2026
Work boundaries: Ross River, South Townsville
Estimated start: Monday 2 March 2026
Expected duration: Four (4) weeks
Normal work hours: From 6am to 6pm Monday to Saturday
Townsville City Council is undertaking vegetation recovery management works along the Ross River adjacent to the Townsville Recreational Boating Park, South Townsville.
This project forms part of Council’s ongoing commitment to environmental management and addresses the need for vegetation recovery works to mitigate the impacts of recent weather events and improve the resilience of the Ross River and its tributaries.
As part of this project, Council will:
- retain informal fishing areas
- remove invasive plant species, with all cleared vegetation mulched for reuse in future Council projects
- undertake revegetation using local native estuarine plant species.
Council staff will oversee water quality and manage any environmental impacts resulting from these operations.
If you live near or are travelling through the area, you may experience:
- construction machinery and vehicle movements
- increased levels of dust, noise, vibrations and occasional odour.

Date published: Monday 2 December 2024
Work boundaries: Sherriff and Archery Park riverbank
Estimated start: Monday 9 December 2024
Expected duration: Current stage: two (2) weeks. Project: until June 2026
Normal work hours: 6am to 6pm, Monday to Saturday
Townsville City Council is undertaking environmental restoration maintenance works along the riverbank to the Ross River within Sherriff and Archery Parks, Mundingburra.
Council began these works in October 2024. We expect maintenance weeding, mulching, and planting to take four months to complete and low-impact maintenance weeding to occur periodically until June 2026.
Council proposes dividing the site into two sections, restricting pedestrian access, and directing pedestrians to an alternative route.
We will close the pedestrian path within each section along the riverbank to suit works progress over the two week period.
Section one is from Sherriff Park to the Mabin Street Park entrance. Section two is from Mabin Street to the midpoint of Archery Park. You can still access the area through the Mabin Street park entrance.
Council will use safety bollards and flagging to mark the work areas and to ensure public safety.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including lane closures, minor traffic delays and reduced speed limits.
Please note: Work will not be continuous across these months but in four stages.



Assistance provided through the jointly-funded Commonwealth-State Disaster Recovery Funding Arrangements (DRFA).
Event Road Closures
Date published: Tuesday 24 December 2024
Work boundaries: Gustav Creek on Sooning Street
Estimated start: Saturday 21 December 2024
Expected duration: Until further notice
Normal work hours: Closed until further notice
Recent heavy rainfall has damaged culverts under the bridge crossing Gustav Creek on Sooning Street and due to community safety concerns Council has closed the bridge.
A preliminary engineering assessment has been conducted and further investigations are required.
Council endeavours to have this additional inspection, and any necessary repairs completed as quickly as possible.
A detour is currently in place via Kelly St, Barton St and Mandalay Ave as signed to access Nelly Bay.
General
Date published: Friday 27 February 2026
Work boundaries: Balgal Beach Campground, Balgal Beach
Estimated start: Monday 9 March 2026
Expected duration: Two (2) weeks
Normal work hours: 6am to 6pm Monday to Saturday
Council is carrying out roofing maintenance on the public amenities block at Balgal Beach Campground, located at the end of the Esplanade in Balgal Beach.
This project is part of Council’s ongoing commitment to asset and infrastructure management. It aims to ensure community assets remain in serviceable condition, supporting regional growth.
As part of this project, Council will:
- remove and replace the roof of the amenities block, carrying out any necessary structural maintenance
- temporary close the park’s amenities block, with Council providing on-site facilities for the duration of the works.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- temporary closure of the amenities block
- increased levels of dust, noise, vibrations and occasional odour.
Date published: Tuesday 3 February 2026
Work boundaries: Big Beach, Cungulla within the blue area on the map
Estimated start: Monday 9 February 2026
Expected duration: Two (2) months
Normal work hours: From 6am to 6pm Monday to Sunday
Council is preparing to undertake remediation work of the Castle Hill Walking Tracks.
This project reflects Council’s ongoing commitment to environmental management, highlighting the importance of remediation efforts to restore the walking tracks to a safe condition.
As part of these works, Council will:
- reinforce track edges
- clear vegetation and rocks
- repair damaged surfaces and remove fallen branches and protruding roots.
If you visit or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- minor closures affecting sections of the walking track.
Please be advised that the Castle Hill walking tracks will remain open throughout the works, with only minor sectional closures in place. Only one track will be worked on at a time. Each track will reopen once it is safe to do so.
Date published: Tuesday 10 March 2026
Work boundaries: Gregory Street, North Ward
Estimated start: Tuesday 17 March 2026
Expected duration: Two (2) weeks
Normal work hours: 6pm to 6am Monday to Saturday
Council is preparing to undertake minor construction works to modify the feature wall on Gregory Street in North Ward.
This initiative supports Council’s commitment to community safety by enhancing roads, transport infrastructure, parks, and water systems – ensuring community connectivity and safety needs are met while continuing to support the growth of our region.
As part of these works, Council will:
- remove the damaged wall corner and construct a new reinforced pillar
- adjust lighting and site tidy up.
If you visit or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary disruptions to vehicle access
- temporary traffic changes, including lane closures, minor traffic delays and reduced speed limits.
Date published: Tuesday 24 June 2025
Work boundaries: Seventh Street, Railway Estate, Bowhunters Road, Condon, Kayleen Court, Burdell
Estimated start: Monday 30 June 2025
Expected duration: Twelve (12) months
Normal work hours: From Monday to Friday 6am to 6pm
Townsville City Council plans to renew the pipework, liners, and associated infrastructure of three wastewater pump stations in Condon, Burdell, and Railway Estate.
This program of works will extend the service life of the existing infrastructure and enhance the reliability and efficiency of the city's wastewater network.
We anticipate work at each site to take three (3) to four (4) months to complete:
- Seventh Street – three (3) months
- Bowhunters Road – three (3) months
- Kayleen Court – four (4) months.
As part of these works, Council will:
- supply and install replacement sewerage pipework and concrete structures
- rehabilitate sewer infrastructure
- restore any disturbed area upon completion of the work.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement within the compounds of the sewer Pump Station.
- increased levels of dust, noise, and vibrations.
These activities will occur within property boundaries and will not require traffic management or lane closures.
Proudly funded by the Queensland Government’s Works for Queensland program.
Date published: Monday 16 March 2026
Work boundaries: Riverway Stadium
Estimated start: Monday 23 March 2026
Expected duration: Two (2) months
Normal work hours: 6am to 6pm Monday to Saturday
Townsville City Council will be renewing all on-field irrigation with a more efficient system designed to reduce water consumption while improving operational performance and ongoing maintenance.
This project reflects Council’s ongoing commitment to delivering parks, sporting fields, recreational spaces, and inspirational gardens that support the health, wellbeing, and enjoyment of our community.
As part of this project, Council will:
- remove the existing on-field irrigation assets
- install new on-field irrigation system, including associated water infrastructure assets
- rectify the disturbed turf areas.
If you live near, visit or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including lane and parking closures, minor traffic delays and reduced speed limits.

Project funded by Townsville City Council.
Date published: Monday 9 March 2026
Work boundaries: Road Corridors around Ross River Road, Aitkenvale and Mundingburra.
Estimated start: Monday 16 March 2026
Expected duration: Two (2) months
Normal work hours: 6am to 6pm Monday to Saturday
Townsville City Council in partnership with a local contractor Jacobs, is planning to undertake geotechnical investigations for the potential sewer main relocation around Ross River Road in Aitkenvale and Mundingburra.
This project is part of Council’s broader long-term investment in water and wastewater systems. It contributes to the city’s Capital Works Program, which is focused on maintaining our community’s water and wastewater infrastructure in optimal condition.
As part of this project, Council will:
- drill test pits, deep boreholes and shallow boreholes
- restore disturbed areas upon completion.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, vibrations and flashing lights
- temporary traffic changes, including lane closures, on-street parking restrictions, minor traffic delays and reduced speed limits.

Project funded by Townsville City Council in partnership with Jacobs.
Date published: Monday 2 March 2026
Work boundaries: Tompkins Road, Shaw
Estimated start: Monday 9 March 2026
Expected duration: Eight (8) months
Normal work hours: 6am to 6pm Monday to Saturday
Townsville City Council is undertaking construction works to deliver a new sewer rising main (wastewater pipeline) to service the Animal Care and Adoption Centre, located along Tompkins Road in Shaw.
This infrastructure upgrade is part of Council’s broader investment in water and wastewater systems, contributing to the city’s $352 million capital works program.
As part of the works, Council will:
- install a new underground wastewater pipeline
- construct a new wastewater pump station
- trenchless crossing of Shaw Road to establish sewer connections
- testing operations and site remediation.
If you live near or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including lane closures, minor traffic delays and reduced speed limits.

Date published: Wednesday 18 March 2026
Work boundaries: Wright Street, Wulguru
Estimated start: Monday 23 March 2026
Expected duration: Three (3) months
Normal work hours: 7am to 6pm Monday to Friday
Townsville City Council is preparing to begin construction of a new, larger diameter sewer pipe on Wright Steet, to redirect wastewater from Glenlyon Drive, Powell and Neelsen Streets in Wulguru.
This will increase capacity of the network, reducing both the volume and frequency of wastewater overflows during wet weather events.
As part of this project, Council will:
- install a new underground sewer line
- conduct testing operations and complete site remediations.
If you live in or are travelling through the area, you may experience:
- construction machinery and increased vehicle movement
- higher levels of dust, noise, and vibrations
- temporary traffic changes, including lane closures, reduced speed limits, minor delays, public transport access and on-street parking closures.
Council will notify impacted properties at least seven days before work begins.

Kerb and Channel
Date published: Friday 6 March 2026
Work boundaries: Emerald Street, Kirwan
Estimated start: Monday 16 March 2025
Expected duration: Eight (8) weeks
Normal work hours: 6am to 6pm Monday to Saturday
Following the recent Design Notification Council is now within the final stages of planning to deliver kerb and channel renewal along Emerald Street between Lanark Street and Andrews Court in Kirwan.
This project is part of our annual Roadworks program, which aims to maintain our Council controlled road network to ensure the community’s transportation needs are adequately met and continue to support the growth of our region.
As part of these works Council will:
- construct kerb and channel and concrete pathway
- reconstruct full and partial driveway crossovers.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including lane closures, minor traffic delays and reduced speed limits.
Council may request residents to relocate their vehicles. Council will notify impacted properties seven days before work begins.

Date published: Friday 23 January 2026
Work boundaries: Between Landsborough Street and #10 Yarrawonga Drive, Castle Hill
Estimated start: Tuesday 03 February 2026
Expected duration: Six (6) weeks
Normal work hours: From 6am to 6pm Monday to Saturday
What works are coming up?
Council is preparing to commence the following stage of Yarrawonga works which will undertake pavement and drainage rehabilitation works between Landsborough Street and #10 Yarrawonga Drive, Castle Hill.
These works will also include the rehabilitation of the service road leading to #4 Yarrawonga Drive.
What will the works include?
As part of these works Council will:
- undertake roadworks as illustrated
- renew sections of kerb and channel and associated pavement
- install kerb inlet grate
- construct trench and dish drains
What does this mean for me?
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including lane closures, minor traffic delays and reduced speed limits

Funding
Project funded by Townsville City Council.
Parks and Playgrounds
Date published: Monday 9 March 2026
Work boundaries: Entrance gate area of Anzac Memorial Park
Estimated start: Monday 9 March 2026
Expected duration: Four (4) weeks
Normal work hours: From 6am to 6pm Monday to Saturday
Council is undertaking gate and fencing maintenance, and infrastructure improvement works in a small section of Anzac Memorial Park, The Strand.
This project is part of Council’s ongoing commitment towards infrastructure management, identifying the need for maintenance works that enhance community assets and preserve open spaces in good condition.
As part of this project, Council will:
- removal of damaged gates and fencing and replacing with new infrastructure
- reshaping foliage in line with natural design principles
- replanting of selected plants, enhanced frontage appeal and carrying out associated groundworks
- Council staff will oversee and manage any environmental impacts resulting from these operations.
If you visit or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, vibrations and occasional odour
- temporary fencing/barriers securing the works zone.

Project funded by Townsville City Council.
Date published: Monday 1 December 2025
Work boundaries: Aplins Weir Rotary Park
Estimated start: Early March 2026
Expected duration: Three (3) months
Normal work hours: From 6am to 6pm Monday to Saturday
Council is now in the final stages of planning the delivery of new public amenities block at Aplins Weir Rotary Park, Mundingburra. The facility will include one accessible toilet cubicle and associated infrastructure, developed in alignment with commitments made during the 2024 Queensland Government Elections.
This initiative reflects the Queensland Government’s dedication to supporting enhancements to existing or future Council infrastructure to better meet the identified needs of the community.
As part of this project, Council will:
- construct a fit-for-purpose single accessible toilet block and associated power, sewer, and water connections
- installation of a new pathway connecting the new facility, demolition of the existing aged facility, minor landscaping, and site remediation works
- preliminary on-site investigation work undertaken by the contractor.
If you visit in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- safety fencing, barricades, and pedestrian/traffic management measures.

This project is proudly funded by the Queensland Government and delivered in partnership with Townsville City Council.
Date published: Tuesday 10 March 2026
Work boundaries: Playground at Belmont Park
Estimated start: Thursday 30 April 2026
Expected duration: Three (3) months
Normal work hours: 6am to 6pm Monday to Saturday
Council is undertaking construction works to deliver the new playground equipment at Belmont Park in Kirwan, aimed at enhancing the park’s functionality and overall amenity.
This initiative reflects Council’s ongoing commitment to providing parks, sporting fields, and recreational spaces that promote the health, wellbeing and enjoyment of our community.
As part of this project, Council will:
- remove the existing playground, sand surfacing and playground edging
- install new playground equipment, along with new sand softfall, and new playground edging
- undertake site remediation.
If you visit in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- safety fencing, barricades, and pedestrian/traffic management measures.

Date published: Friday 13 March 2026
Work boundaries: Dan Gleeson Memorial Gardens, Kirwan
Estimated start: Monday 23 March 2026
Expected duration: Two (2) weeks
Normal work hours: 6am to 6pm Monday to Saturday
Townsville City Council will be undertaking repairs of canopy sprinklers at Dan Gleeson Memorial Gardens, Kirwan as part of flying-fox management at the park.
To undertake these works council will be undertaking more intensive ‘nudging’ works from approximately 5am to 8am daily.
These works form part of Council’s ongoing commitment to the ecologically sustainable management of flying fox roosts, undertaken in accordance with the Code of Practice – Ecologically Sustainable Management of Flying Fox Roosts.
As part of this project, Council will:
- undertake approved flying-fox nudging management practices
- undertake repair and use of canopy sprinklers
- Council staff will oversee and manage any environmental impacts resulting from these operations.
If you visit in or are travelling through the area, you may experience:
- loud noises associated with disposal techniques
- movement of small machinery in the park
- operation of canopy sprinklers
- increased activity from Council officers and contractors in the area
- possible changes to flying-fox movement patterns during the works.
Date published: Friday 27 February 2026
Work boundaries: Riverside Green, Douglas
Estimated start: Monday 9 March 2026
Expected duration: Two (2) months
Normal work hours: 6am to 6pm Monday to Saturday
Council is undertaking construction works for the installation of a new public amenities block at Riverside Green, Douglas. This facility will include one accessible toilet cubicle and associated infrastructure, developed in alignment with commitments made during the 2024 Queensland Government Elections.
This initiative reflects the Queensland Government’s dedication to supporting enhancements to existing or future Council infrastructure to better meet the identified needs of the community.
As part of this project, Council will:
- construct a fit-for-purpose single accessible toilet block and associated power, sewer, and water connections
- install a new pathway connecting the new facility
- perform minor landscaping and site remediation works.
If you visit in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- safety fencing, barricades, and pedestrian/traffic management measures.
This project is proudly funded by the Queensland Government and delivered in partnership with Townsville City Council.

Date published: Monday 9 March 2026
Work boundaries: Six shade structures in Strand Park
Estimated start: Monday 9 March 2026
Expected duration: Four (4) weeks
Normal work hours: 6am to 6pm Monday to Saturday
Council is undertaking infrastructure maintenance and refurbishment works on six shade structures located adjacent to Strand Park on The Strand.
This project forms part of Council’s ongoing commitment to infrastructure management, identifying the need for maintenance works that enhance community assets and preserve open spaces in good condition.
As part of this project, Council will:
- undertake detailed maintenance work on the structure to ensure an ongoing safe and optimal shaded seating area for the community
- Council staff will oversee and manage any environmental reinstatement work resulting from these operations.
If you visit or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- temporary closure of a section of the six shade structures, as indicated overleaf
- increased levels of dust, noise, vibrations and occasional odour.
Three structures will be closed at one time, and once the work is complete, they will reopen.

Project funded by Townsville City Council.
Pathway Works
Date published: Monday 16 March 2026
Work boundaries: Damaged sections of the pathway at identified locations within the suburban catchment area of Douglas.
Estimated start: Monday 23 March 2026
Expected duration: Six (6) weeks
Normal work hours: From 6am to 6pm Monday to Saturday
Council is planning to deliver pathway renewal works on damaged sections of the pathway at identified locations within the suburban catchment area of Douglas.
This project is part of Council’s commitment to taking a Back to Basics approach, delivering the services our community expects to continue growing Townsville.
These works will include:
- removal of damaged sections of the pathway
- installation of new concrete replacement
- reinstatement of pathway connections to restore functionality and appearance.
If you visit or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporarily close the affected section of the pathway and implement a signed detour rout to guide pedestrians effectively.
Project funded by Townsville City Council.
Date published: Tuesday 17 March 2026
Work boundaries: Gregory Street, North Ward
Estimated start: Tuesday 24 March 2026
Expected duration: Two (2) days
Normal work hours: 6am to 6pm Monday to Saturday
Townsville City Council will be undertaking maintenance works on a section of pathway along Gregory Street, adjacent to 58 The Strand, North Ward.
This project forms part of Council’s ongoing commitment to infrastructure management. The works aim to enhance community assets, improve safety and accessibility, and ensure pathways remain in good condition.
As part of these works, Council will:
- removal of all existing pavers and installation of temporary asphalt
- reinstatement of pathway connections to restore full functionality and appearance.
If you visit or are travelling through the area, you may experience:
- movement of construction vehicles and machinery
- increased dust, noise and vibration levels
- temporary closure of the identified section of pathway and adjacent car park
- signed detours redirecting pedestrians safely.
Date published: Wednesday 21 January 2026
Work boundaries: Jezzine Boardwalk, North Ward
Estimated start: Wednesday 28 January 2026
Expected duration: Two (2) months
Normal work hours: From 6am to 6pm Monday to Saturday
What works are coming up?
Council is undertaking infrastructure maintenance and refurbishment works on the timber bridged railing sections of the raised boardwalk located in North Ward.
This project forms part of Council’s ongoing commitment to infrastructure management, addressing identified maintenance needs to ensure community assets are maintained in a safe and serviceable condition.
What will the works include?
As part of this project, Council will:
- undertake detailed maintenance work on the boardwalk bridge railing to ensure an ongoing safe and optimal connection for the community
- Council staff will oversee and manage any environmental reinstatement work resulting from these operations.
What does this mean for me?
If you visit or are travelling through the area, you may experience:
- increased levels of dust, noise, vibrations and occasional odour.
- maintenance works will be completed in sections resulting in no access closures required.

Funding
Project funded by Townsville City Council.
Date published: Monday 9 March 2026
Work boundaries: Along Victoria Bridge with access ramp closures
Estimated start: Monday 16 March 2026
Expected duration: Six (6) weeks
Normal work hours: 6am to 6pm Monday to Friday
Council is undertaking maintenance works on the walking surface of Victoria Bridge between Ogden Street and Dean Street, Townsville City.
This initiative forms part of Council’s annual Infrastructure Maintenance Program, which ensures essential assets remain safe, functional, and capable of supporting the region’s growing connectivity needs.
As part of the works, Council will:
- temporarily close both access ramps and implement a detour for those unable to use the stairs
- overlay deteriorated walking surface with new, fit-for-purpose non-slip materials
- conduct substructure repairs as required.
If you live near, or are travelling through the area, you may experience:
- temporary fencing on the bridge
- higher levels of dust, noise, and vibrations
- temporary closure of bridge access ramps from 16 to 24 March 2026, with a detour in place.
The bridge will remain open for the duration of the project, with no impact to access via the stairs at either end.

Project funded by Townsville City Council.
Roadworks
Date published: Tuesday 24 February 2026
Work boundaries: Boundary Street, South Townsville
Estimated start: Tuesday 3 March 2025
Expected duration: Four (4) weeks
Normal work hours: From 6am to 6pm Monday to Saturday
Council is preparing to undertake roadworks along Boundary Street between Samphire Drive and Fourth Avenue.
This project is part of our annual Roadworks program, which aims to maintain our Council controlled road network to ensure the community’s transportation needs are adequately met and continue to support the growth of our region.
As part of this project, Council will:
- construct kerb and channel, new sections of footpath and a new stormwater pit
- replace identified sections of driveway crossovers
- install grated inverted box culverts
- construct standard crossovers matching associated driveways.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including lane closures, minor traffic delays and reduced speed limits.

Date published: Friday 25 July 2025
Work boundaries: Freshwater Drive, Douglas
Estimated start: Monday 28 July 2025
Expected duration: Two (2) weeks
Normal work hours: 6am to 6pm Monday to Saturday
Council is undertaking operational road maintenance along Freshwater Drive between Lord Howe Promenade and Estuary Parade in Douglas.
This project is part of Council’s annual Operational Roadworks program, which aims to maintain our Council controlled road network to ensure the community’s transportation needs are adequately met and continue to support the growth of our region.
As part of this project, Council will:
- construct a centre median pedestrian refuge, including associated line markings
- install concrete ramping and footpath connections, matched neatly to existing infrastructure.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including lane closures, minor traffic delays and reduced speed limits.
Date published: Friday 19 December 2025
Work boundaries: Goodsell Road between Meenan Road and Frank Randell Drive, Cape Cleveland
Estimated start: Tuesday 6 January 2026
Expected duration: Two (2) months
Normal work hours: 6am to 6pm Monday to Saturday
Council is undertaking roadworks on Goodsell Road, between the street boundaries of Meenan Road and Frank Randell Drive in Cape Cleveland. The works include the installation of road verge speed warning signage and road improvements designed to enhance road safety.
This project forms part of Council’s annual Roadworks program, which aims to maintain or improve our Council controlled road network. The program ensures our community’s connectivity needs are met and continues to support the growth of our region.
Works include:
- Installation of designated road informational and directional signage including minor roadworks
- painting road markings and installation of reflective markers or signage.
If you live near or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including minor traffic delays and reduced speed limits.

Roadworks zone indicated via the blue shade outline above
Funding
This project is proudly funded by the Australian Government Blackspot program – an Australian Government road safety initiative, that aims to improve road safety and delivered in partnership with Townsville City Council.
Date published: Tuesday 27 January 2026
Work boundaries: Gulliver and Hugh Streets from Palmerston Street to Ross River Road
Estimated start: Early February 2026
Expected duration: Four (4) weeks
Normal work hours: From 6am to 6pm Monday to Saturday
What works are coming up?
Townsville City Council plans to upgrade active transport facilities along Gulliver and Hugh Streets between Woolcock Street and Ross River Road. The active transport facilities upgrade intends to improve the safety, efficiency, and functionality of Gulliver and Hugh Streets for pedestrians and cyclists.
Council will deliver this project in stages:
- Stage One – Palmerston Street to Ross River Road (eastern side)
- Stage Two – Ross River Road to Palmerston Street (western side)
- Stage Three – Palmerston Street to Woolcock Street (western side)
- Stage Four – Woolcock Street to Palmerston Street (eastern side)
What will the works include?
As part of this project, Council will construct 2.5km of 2.5m-wide shared pathway, 1.5m-wide footpath sections and line mark on-road bicycle lanes.
Additionally, we will:
- install raised priority crossings at minor road intersections
- install a signalised SMART pedestrian crossing near the Wellington Street intersection
- replace sections of existing driveways, reconstruct driveways, driveway crossovers, and associated kerb and channel
- construct concrete medians, cycle and pedestrian ramps.
What does this mean for me?
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including lane closures, minor traffic delays and reduced speed limits.

Funding
Project funded by Townsville City Council.
Date published: Tuesday 3 February 2026
Work boundaries: Hugh Street, Currajong
Estimated start: Tuesday 10 February 2026
Expected duration: Five (5) weeks
Normal work hours: 6am to 6pm Monday to Saturday
Townsville City Council is continuing the delivery of active transport facilities along Gulliver and Hugh Streets, between Woolcock Street and Ross River Road. With the first and second stages well underway, an opportunity has arisen to allocate an additional construction crew to commence works on Stage 3.
This project is part of Council’s active transport upgrade program, which aims to maintain and enhance our Council controlled active transport infrastructure network to ensure the community’s connectivity needs are adequately met and continue to support the growth of our region.
As part of this project, Council will:
- construct shared concrete footpath
- install raised priority crossings at identified road intersections
- replace identified sections of driveway crossovers, and associated kerb and channel
- construct concrete medians, and install designated on-road bicycle lanes
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including lane and on-street parking closures, minor traffic delays and reduced speed limits.
Date published: Monday 9 March 2026
Work boundaries: Murray Street, between Gregory and Stokes Streets, North Ward.
Estimated start: November 2025
Expected duration: Seven (7) months
Normal work hours: 6am to 6pm Monday to Saturday.
Townsville City Council is continuing the delivery of the Murray Street Roadworks and Services Upgrade between Gregory and Victoria Street, North Ward.
This project is part of Council’s Capital Works program, which ensures community transport, stormwater, water and sewerage infrastructure continues to meet the needs of our growing region.
As part of this project, Council will:
- repair and replace the top layer of the road surface to improve its condition and extend pavement lifespan
- renew and replace existing water and wastewater pipes to improve service reliability and reduce the risk of future disruptions.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including lane and on-street parking closures, minor traffic delays and reduced speed limits.
Please be advised there will be a short pause in construction from 30 March to 6 April 2026 for the Easter holiday period.

This project is proudly funded by the Queensland Government’s Works for Queensland Program.
Date published: Monday 15 September 2025
Work boundaries: No Name Road south to Bidwilli Road.
Estimated start: Thursday 17 September 2025
Expected duration: Seven (7) months
Normal work hours: 6am to 6pm Monday to Saturday.
Council will be carrying out work to extend No Name Road south to Bidwilli Road. The project includes upgrading the Ghost Gum Road and Bidwilli Road intersections to connect with No Name Road, and creating new northern access from DriveIt NQ along Ghost Gum Road to No Name Road.
These works form part of the enabling infrastructure for the Lansdown Eco‑Industrial Precinct and will be delivered by civil contractor BMD Constructions.
These works will include:
- Applying the final road seal to the existing section of No Name Road.
- Extending pavement from the existing section of No Name Road south to Bidwilli Road.
- Constructing new road pavement from DriveIt NQ along Ghost Gum Road to No Name Road.
- Upgrading the No Name Road / Ghost Gum Road and No Name Road / Bidwilli Road intersections.
- Installing new culverts and drainage structures to improve stormwater flow.
- Providing flag lighting at intersections, along with line marking, signage, and fencing.
If you live in or are travelling through the area, you may experience:
- Construction machinery and vehicle movement.
- Increased levels of dust, noise, and vibrations.
- Temporary traffic changes, including lane closures, temporary traffic lights, minor traffic delays and reduced speed limits.
Lansdown Eco-Industrial Precinct is Jointly funded by the Australian Government and Queensland Government, in association with Townsville City Council.
Date published: Monday 16 March 2026
Work boundaries: Ring Road from Douglas to Deeragun
Estimated start: Saturday 21 March 2026
Expected duration: One (1) night
Normal work hours: 9pm to 6am Saturday to Sunday
Council is undertaking scheduled cleaning works along the Ring Road, starting from the on and off ramps in front of Lavarack Barracks through to the on and off ramps next to the BIG4 Ingenia Holiday Park in Deeragun.
These works form part of Council’s annual Roadworks Program, which aims to maintain our high-traffic road network to ensure it remains safe, meets the community’s transport needs, and continues to support the growth of our region.
As part of this project, Council will:
- undertake detailed cleaning, remove rubbish, and carry out minor road refurbishment works.
If you are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including road closures, minor traffic delays and reduced speed limits
- temporary Ring Road closure from the on/off ramp in front of Lavarack Barracks to the on/off ramps adjacent to the Big4 Ingenia Holiday Park.
This project is proudly funded by the Queensland Government and delivered in partnership with Townsville City Council.
Trees
Date published: Wednesday 25 February 2026
Work boundaries: River Park Drive, Annandale
Estimated start: Wednesday 4 March 2025
Expected duration: Two (2) days
Normal work hours: 6am to 6pm Monday to Saturday
Council’s Principal Arborist has recently completed a detailed inspection on a large African Mahogany (Khaya) tree positioned within the nature reserve adjacent to 49 River Park Drive, Annandale.
The decision to remove this tree was made based on the certified arborist’s report, which confirms that the tree has died and has become a risk to the surrounding infrastructure and a high risk to public safety.
Unfortunately, no further arboriculturally management practices can be recommended to safely retain the tree.
Works will include removal of the tree branches and mulching. Suitable replacement trees will be planted near the removed tree to replace the equivalent lost canopy cover.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including lane closures, minor traffic delays and reduced speed limits.
Date published: Friday 13 March 2026
Work boundaries: Walker Street Car Park, Townsville City
Estimated start: Saturday 21 March 2025
Expected duration: Four (4) hours
Normal work hours: 7am to 11am Saturday
Council’s Principal Arborist has recently undertaken an inspection of all trees located within the Walker Street car park (section fronting Walker Street), Townsville City.
Maintenance work will be carried out on all designated trees within the highlighted section. This includes the removing identified branches and associated foliage to prevent obstruction or hazards to vehicles and pedestrians, and to support the long-term health of our urban tree canopy.
Works will include removal of identified tree branches and mulching of removed material. Council arborists will oversee all landscaping maintenance to ensure tree health, reduce risk to infrastructure, and maintain community safety.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movements
- increased levels of dust, noise, and vibration
- temporary traffic changes, including partial car park section closure, minor commuter delays and reduced speed limits.
The affected section of the car park will be closed from 7am and is scheduled to reopen by 11am, or earlier if safe to do so. The remainder of the car park will remain open outside the designated work zone.

Water Mains
Date published: Tuesday 10 March 2026
Work boundaries: Duggan Drive, Alligator Creek
Estimated start: Thursday 12 March 2026
Expected duration: One (1) day
Normal work hours: From 8am to 2pm
What works are coming up?
Townsville City Council is undertaking essential water infrastructure works in Duggan Drive, Alligator Creek, resulting in a temporary interruption to properties’ water supply as outlined below. These works are part of Council’s long-term investment in securing our water and wastewater systems, ensuring that the city’s connectivity infrastructure is maintained in optimal condition.
What will the works include?
As part of this project, Council will:
- install or repair water pipelines, pump stations, and/or major trunk lines
- restore the work area to its original condition after completion.
What does this mean for me?
If you live in or are travelling through the area, you may experience:
- increased noise, dust and vibrations from construction vehicles and equipment in the area
- temporary short term water supply interruptions.
Please note that sufficient water should be stored in containers prior to 8am on this day if required and automatic washing machines should be turned off during water outages.
Important: When the water supply is restored there initially may be discolouration. The team will flush the system in your area to minimise this; however, you may need to run your taps until the supply clears.

Date published: Wednesday 18 March 2026
Work boundaries: Howlett Street, Currajong
Estimated start: Friday 20 March 2026
Expected duration: One (1) day
Normal work hours: From 8am to 2pm
What works are coming up?
Townsville City Council is undertaking essential water infrastructure works in Howlett Street, Currajong, resulting in a temporary interruption to properties’ water supply as outlined below. These works are part of Council’s long-term investment in securing our water and wastewater systems, ensuring that the city’s connectivity infrastructure is maintained in optimal condition.
What will the works include?
As part of this project, Council will:
- install or repair water pipelines, pump stations, and/or major trunk lines
- restore the work area to its original condition after completion.
What does this mean for me?
If you live in or are travelling through the area, you may experience:
- increased noise, dust and vibrations from construction vehicles and equipment in the area
- temporary short term water supply interruptions.
Please note that sufficient water should be stored in containers prior to 8am on this day if required and automatic washing machines should be turned off during water outages.
Important: When the water supply is restored there initially may be discolouration. The team will flush the system in your area to minimise this; however, you may need to run your taps until the supply clears.

Date published: Tuesday 11 November 2025
Work boundaries: Mount Low Reservoir, Bushland Beach
Estimated start: Tuesday 18 November 2025
Expected duration: Six (6) months
Normal work hours: From 6am to 6pm Monday to Saturday
Council is undertaking construction works to deliver the renewal of Water Tank 1 at the Mount Low Reservoir, located at Euskadi Court in Bushland Beach.
This initiative reflects Council’s commitment to investing $352 million this year to enhance roads, transport infrastructure, parks, and water systems – ensuring that all properties continue to receive efficient and reliable water service.
As part of this project, Council will:
- renovate the reservoir roof.
- install access ladders and platforms.
- replace pipework.
- reinstate corrosion protection.
- apply a new internal protective coating to the tank.
If you live near or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
Council advises that renewal works affect Water Tank 1 only. Water Tank 2 will remain operational and continue servicing residents.
Project proudly funded by the Queensland Government’s Works for Queensland program and delivered in partnership with Townsville City Council.

Date published: Wednesday 18 March 2026
Work boundaries: South Vickers Road, Condon
Estimated start: Friday 20 March 2026
Expected duration: One (1) day
Normal work hours: From 8am to 2pm
What works are coming up?
Townsville City Council is undertaking essential water infrastructure works in South Vickers Road, Condon, resulting in a temporary interruption to properties’ water supply as outlined below. These works are part of Council’s long-term investment in securing our water and wastewater systems, ensuring that the city’s connectivity infrastructure is maintained in optimal condition.
What will the works include?
As part of this project, Council will:
- install or repair water pipelines, pump stations, and/or major trunk lines
- restore the work area to its original condition after completion.
What does this mean for me?
If you live in or are travelling through the area, you may experience:
- increased noise, dust and vibrations from construction vehicles and equipment in the area
- temporary short term water supply interruptions.
Please note that sufficient water should be stored in containers prior to 8am on this day if required and automatic washing machines should be turned off during water outages.
Important: When the water supply is restored there initially may be discolouration. The team will flush the system in your area to minimise this; however, you may need to run your taps until the supply clears.

Recently Completed
| Location | Works | Description |
|---|---|---|
| Castle Hill Road, Castle Hill | Vegetation Maintenance Works | Completed vegetation maintenance. |
| Williams Road, Alligator Creek | Water Interruption Works | Completed maintenance to water main |
| Hammond Way, Kelso | Water Interruption Works | Completed maintenance to water main |
| Arcadia Road, Magnetic Island Road and Horseshoe Bay Road, Magnetic Island | Slope Risk Assessment | Slope Risk Assessment Completed |
| Riverway Drive, Kelso | Water Interruption Works | Completed maintenance to water main |
| Granville Street, Pimlico | Granville Street, Pimlico | Completed maintenance to water main |
| Cuthbert Crescent, Vincent | Water Interruption Works | Completed maintenance to water main |
| Cay Street, Saunders Beach | Water Interruption Works | Completed maintenance to water hydrant |
| Nelson Street, South Townsville | Water Interruption Works | Completed maintenance to water main |
| Cameron Court, Kelso | Water Interruption Works | Completed maintenance to water main |
| Portland Street, Hyde Park | Water Interruption Works | Completed maintenance to water main |
| Nix Street, West End | Water Interruption Works | Completed maintenance to water main |
| Riverway Drive & Rosewood Avenue, Kelso | Water Interruption Works | Completed maintenance to water main |
| Percy Street, West End | Water Interruption Works | Completed maintenance to water main |
| Gibraltar Road, Rangewood | Water Interruption Works | Completed maintenance to water hydrant |
| Basildon Close, Burdell | Water Interruption Works | Completed maintenance to water main |
| Eyre Street, North Ward | Water Interruption Works | Completed maintenance to water main |
| Arila Street, Cranbrook | Water Interruption Works | Completed maintenance to water main |
| Ewen Jones Bridge, Garbutt | Maintenance Works | Completed bridge maintenance |
| Hugh Street, Mundingburra | Gulliver and Hugh Streets Active Transport Facilities Upgrade – Stage One | Roadworks completed |


