You are here: Home Building, Planning & Projects Works & Road Closures List View
Works & Road Closures List View
Townsville City Council is committed to delivering well-maintained infrastructure and efficient transportation systems, with over $400 million being invested in roads and transport management, open spaces, water, and wastewater management this financial year.
This page contains works and road closures currently underway or planned in a screen reader friendly list. To view the interactive map version, visit Works & Road Closures.
For State Government road works and closures, visit Queensland Government Traffic and Travel Information.
Disclaimer: Information should be used as a guide only. Dates and times relating to the works are estimates and may be impacted by weather and project conditions.
Drainage
Date published: Friday 19 December 2025
Work boundaries: Winifred Street, Mundingburra
Estimated start: Thursday 25 December 2025
Expected duration: Four (4) months
Normal work hours: 6am to 6pm Monday to Saturday
Council is continuing flood and drainage improvement works along Winifred Street. With the second stage of preliminary preloading works along the Ross River riverbank nearing completion, the project will now pause to allow the preloading to settle before progressing to the next stage.
This project is part of Council’s stormwater Capital Works program, designed to address and improve drainage across Council’s networks, and raise the quality of life for residents.
What will the works include? As part of this project, Council will:
- demobilise laydown site and undertake revegetation
- reinstate temporary vegetation upon completion of preloading activities, in preparation for the final stage of the project
- re-establish the shared pedestrian path connection along the Ross River
- continue monitoring the preloading works throughout this short construction pause.
If you live in or are travelling through the area, you may experience:
- minimal construction machinery and vehicle movement
- Council will provide an update notification before the projects move into the final stage of construction.
Funding
Project funded by Townsville City Council.
Environmental Restoration
Date published: Monday 2 December 2024
Work boundaries: Sherriff and Archery Park riverbank
Estimated start: Monday 9 December 2024
Expected duration: Current stage: two (2) weeks. Project: until June 2026
Normal work hours: 6am to 6pm, Monday to Saturday
Townsville City Council is undertaking environmental restoration maintenance works along the riverbank to the Ross River within Sherriff and Archery Parks, Mundingburra.
Council began these works in October 2024. We expect maintenance weeding, mulching, and planting to take four months to complete and low-impact maintenance weeding to occur periodically until June 2026.
Council proposes dividing the site into two sections, restricting pedestrian access, and directing pedestrians to an alternative route.
We will close the pedestrian path within each section along the riverbank to suit works progress over the two week period.
Section one is from Sherriff Park to the Mabin Street Park entrance. Section two is from Mabin Street to the midpoint of Archery Park. You can still access the area through the Mabin Street park entrance.
Council will use safety bollards and flagging to mark the work areas and to ensure public safety.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including lane closures, minor traffic delays and reduced speed limits.
Please note: Work will not be continuous across these months but in four stages.



Assistance provided through the jointly-funded Commonwealth-State Disaster Recovery Funding Arrangements (DRFA).
Event Road Closures
Date published: Tuesday 24 December 2024
Work boundaries: Gustav Creek on Sooning Street
Estimated start: Saturday 21 December 2024
Expected duration: Until further notice
Normal work hours: Closed until further notice
Recent heavy rainfall has damaged culverts under the bridge crossing Gustav Creek on Sooning Street and due to community safety concerns Council has closed the bridge.
A preliminary engineering assessment has been conducted and further investigations are required.
Council endeavours to have this additional inspection, and any necessary repairs completed as quickly as possible.
A detour is currently in place via Kelly St, Barton St and Mandalay Ave as signed to access Nelly Bay.
General
Date published: Tuesday 13 January 2026
Work boundaries: Arcadia Road, Magnetic Island Road and Horseshoe Bay Road, Magnetic Island
Estimated start: February 2026
Expected duration: Two (2) days
Normal work hours: From 6am to 6pm
What works are coming up?
Townsville City Council has identified four (4) key slopes along the Magnetic Island road network that require remediation to ensure safety and long‑term stability. As part of this work, Council will be carrying out detailed slope risk assessments at each of the proposed locations. Further information will be shared with the community as we get closer to the start of works.
What will the works include?
As part of this project, Council will:
- Carry out on‑foot surveys to collect detailed data at each site
- Undertake geotechnical investigations
What does this mean for me?
If you live in or are travelling through the area, you may experience:
- Contractor personnel and vehicle movement
- Temporary traffic changes, including lane closures, minor traffic delays and reduced speed limits


Funding
Project funded by Townsville City Council.
A local contractor, Jacobs, is delivering these works on behalf of Council.
Date published: Tuesday 16 December 2025
Work boundaries: Big Beach, Cungulla within the blue area on the map
Estimated start: Monday 22 December 2025
Expected duration: One (1) day
Normal work hours: From 6am to 6pm
What works are coming up?
Coastal aerial surveys will be conducted along Big Beach, bordering northern George Ansell Avenue and Cooldetta Street, Cungulla to assess sand volume distribution and natural coastal resilience. This information will inform ongoing and future sustainable management actions.
This project is part of Council’s ongoing commitment to sustainable environmental management, recognising the valuable role ongoing coastal monitoring plays in environmental resilience and erosion management practices.
What will the works include?
As part of these works, Council will undertake:
- drone flyovers
- coastal investigations.
What does this mean for me?
If you live in or are travelling through the area, you may experience:
- whirring noises from drones
- drone lights in the sky.
Drone operations will avoid flying over private properties and will not interfere with or impact the community.
Map of works location
Works will occur within the blue area indicated on the map.

Funding
This project is funded by Townsville City Council.
Date published: Tuesday 23 December 2025
Work boundaries: Gustav Creek, Nelly Bay
Estimated start: Thursday 8 January 2025
Expected duration: Two weeks
Normal work hours: From 6am to 6pm Monday to Saturday
What works are coming up?
In December 2025, machinery and equipment arrived by barge and were transported to the project site under oversized load escort, including 24 piles measuring 18 metres each.
Townsville City Council plans to begin pile installation in early January 2026.
These works will cause disruption to nearby residents, businesses and visitors to the area. Depending on how close you are to the construction work, noise will be noticeable.
Piling work will create noise as we pre-drill holes and drive the piles into the ground. These types of work are often intense, and the noise and vibration can be intense too. This is all normal and expected during piling works.
When will the works take place?
Pile installation activities will take place from Thursday 8 January 2025 and are expected to take two weeks to complete, weather and project conditions permitting.
What will the works include?
As part of this stage, Council contractor, BMD Constructions will:
- bore 12 holes at pile locations
- drive 12 piles, 14 metres deep, into the ground
- splice 12 piles onto the lower piles driven first
- drive the attached upper piles to the design depth.
What does this mean for me?
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including lane closures, minor traffic delays and reduced speed limits.

Funding
This project is financed through the jointly funded Commonwealth-state Disaster Recovery Funding Arrangements (DRFA).
Date published: Tuesday 24 June 2025
Work boundaries: Seventh Street, Railway Estate, Bowhunters Road, Condon, Kayleen Court, Burdell
Estimated start: Monday 30 June 2025
Expected duration: Twelve (12) months
Normal work hours: From Monday to Friday 6am to 6pm
Townsville City Council plans to renew the pipework, liners, and associated infrastructure of three wastewater pump stations in Condon, Burdell, and Railway Estate.
This program of works will extend the service life of the existing infrastructure and enhance the reliability and efficiency of the city's wastewater network.
We anticipate work at each site to take three (3) to four (4) months to complete:
- Seventh Street – three (3) months
- Bowhunters Road – three (3) months
- Kayleen Court – four (4) months.
As part of these works, Council will:
- supply and install replacement sewerage pipework and concrete structures
- rehabilitate sewer infrastructure
- restore any disturbed area upon completion of the work.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement within the compounds of the sewer Pump Station.
- increased levels of dust, noise, and vibrations.
These activities will occur within property boundaries and will not require traffic management or lane closures.
Proudly funded by the Queensland Government’s Works for Queensland program.
Date published: Wednesday 29 October 2025
Work boundaries: Locations throughout Railway Estate
Estimated start: Mid-November 2025
Expected duration: Three (3) months
Normal work hours: From 6am to 6pm Monday to Saturday
Townsville City Council is undertaking sewer pipe and maintenance hole inspections of the network in locations throughout Railway Estate.
This program allows Council to undertake condition assessments as part of our network maintenance strategy. The data collected by these surveys will allow Council to plan for future rehabilitation and replacement work.
Council has appointed Interflow Pty Ltd to carry out this project on our behalf.
To proceed with these works, Interflow may require access to clean the sewer maintenance hole and the associated wastewater pipeline within and adjacent to your property boundary.
Interflow will advise you via a letter drop if access is required into your property.
As part of this project, Council will:
- inspect sewer pipe and maintenance holes with CCTV camera surveys
- clean and flush sewers and underground pipework by jetting
- restore any disturbed area upon works completion.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of noise, and vibrations
- temporary traffic changes, including lane closures, minor traffic delays and reduced speed limits.
Project funded by Townsville City Council and is being delivered by local contractor.

Date published: Friday 28 November 2025
Work boundaries: Whitehouse Street, Garbutt. between Bayswater Road and 4 Whitehouse Street
Estimated start: Tuesday 2 December 2025
Expected duration: Eight (8) weeks
Normal work hours: From 6am to 6pm Monday to Saturday
What works are coming up?
Townsville City Council is preparing to commence a sewer diversion project along Whitehouse Street.
The project is to replace aging infrastructure that is no longer accessible to maintain. The work will increase resilience of the sewer network during wet weather.
What will the works include?
As part of these works Council will:
- manage traffic along Whitehouse Street
- use heavy machinery for excavation of road shoulder
- construct sewer manholes and pipework
- re-instate road sub-grade and road pavement
What does this mean for me?
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary disruptions to vehicle access to properties and some on street parking
- temporary traffic changes, including lane closures, minor traffic delays and reduced speed limits
Funding
Project funded by the Townsville City Council.

Parks and Playgrounds
Date published: Monday 1 December 2025
Work boundaries: Aplins Weir Rotary Park
Estimated start: Early March 2026
Expected duration: Three (3) months
Normal work hours: From 6am to 6pm Monday to Saturday
What works are coming up?
Council is now in the final stages of planning the delivery of new public amenities block at Aplins Weir Rotary Park, Mundingburra. The facility will include one accessible toilet cubicle and associated infrastructure, developed in alignment with commitments made during the 2024 Queensland Government Elections.
This initiative reflects the Queensland Government’s dedication to supporting enhancements to existing or future Council infrastructure to better meet the identified needs of the community.
What will the works include?
As part of this project, Council will:
- construct a fit-for-purpose single accessible toilet block and associated power, sewer, and water connections
- installation of a new pathway connecting the new facility, demolition of the existing aged facility, minor landscaping, and site remediation works
- preliminary on-site investigation work undertaken by the contractor.
What does this mean for me?
If you visit in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- safety fencing, barricades, and pedestrian/traffic management measures.
Funding
This project is proudly funded by the Queensland Government and delivered in partnership with Townsville City Council.

Date published: Tuesday 14 October 2025
Work boundaries: Oonoonba Park, Oonoonba,
Estimated start: Monday, 20 October 2025
Expected duration: Three (3) months
Normal work hours: From 6am to 6pm Monday to Saturday
Council is now in the final stages of planning the delivery of new playground equipment and associated infrastructure at Oonoonba Park, Oonoonba, following damage caused by vandals who set fire to the previous equipment last year.
This initiative reflects Council’s commitment to providing parks, sporting fields and recreational space that enhance the health, wellbeing and enjoyment of our community.
As part of this project, Council will:
- remove the existing playground, rubber surfacing, and any remaining shade sail pieces or fire debris
- install like-for-like replacement playground equipment, including rubber softfall and concrete edging
- install a replacement shade sail along with landscaping and site remediation works.
If you visit in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- safety fencing, barricades, and pedestrian/traffic management measures.


Project funded by Townsville City Council.
Roadworks
Date published: Friday 25 July 2025
Work boundaries: Freshwater Drive, Douglas
Estimated start: Monday 28 July 2025
Expected duration: Two (2) weeks
Normal work hours: 6am to 6pm Monday to Saturday
Council is undertaking operational road maintenance along Freshwater Drive between Lord Howe Promenade and Estuary Parade in Douglas.
This project is part of Council’s annual Operational Roadworks program, which aims to maintain our Council controlled road network to ensure the community’s transportation needs are adequately met and continue to support the growth of our region.
As part of this project, Council will:
- construct a centre median pedestrian refuge, including associated line markings
- install concrete ramping and footpath connections, matched neatly to existing infrastructure.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including lane closures, minor traffic delays and reduced speed limits.
Date published: Friday 19 December 2025
Work boundaries: Goodsell Road between Meenan Road and Frank Randell Drive, Cape Cleveland
Estimated start: Tuesday 6 January 2026
Expected duration: Two (2) months
Normal work hours: 6am to 6pm Monday to Saturday
Council is undertaking roadworks on Goodsell Road, between the street boundaries of Meenan Road and Frank Randell Drive in Cape Cleveland. The works include the installation of road verge speed warning signage and road improvements designed to enhance road safety.
This project forms part of Council’s annual Roadworks program, which aims to maintain or improve our Council controlled road network. The program ensures our community’s connectivity needs are met and continues to support the growth of our region.
Works include:
- Installation of designated road informational and directional signage including minor roadworks
- painting road markings and installation of reflective markers or signage.
If you live near or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including minor traffic delays and reduced speed limits.

Roadworks zone indicated via the blue shade outline above
Funding
This project is proudly funded by the Australian Government Blackspot program – an Australian Government road safety initiative, that aims to improve road safety and delivered in partnership with Townsville City Council.
Date published: Monday 22 December 2025
Work boundaries: Hugh Street from Palmerston Street to Ross River Road
Estimated start: Tuesday 6 January 2026
Expected duration: Six (6) weeks
Normal work hours: 6am to 6pm Monday to Saturday
Townsville City Council plans to upgrade active transport facilities along Gulliver and Hugh Streets between Woolcock Street and Ross River Road. The active transport facilities upgrade intends to improve the safety, efficiency, and functionality of Gulliver and Hugh Streets for pedestrians and cyclists. This project forms part of Council's annual Roadworks program, which aims to maintain or improve our Council controlled road network. The program ensures our community's connectivity needs are met and continues to support the growth of our region.
Council will deliver this project in stages:
- Stage One – Palmerston Street to Ross River Road (eastern side)
- Stage Two – Ross River Road to Palmerston Street (western side)
- Stage Three – Palmerston Street to Woolcock Street (western side)
- Stage Four – Woolcock Street to Palmerston Street (eastern side)
As part of these works Council will construct 2.5km of 2.5m-wide shared pathway, 1.5m-wide footpath sections and line mark on-road bicycle lanes.
Additionally, we will:
- install raised priority crossings at minor road intersections
- install a signalised SMART pedestrian crossing near the Wellington Street intersection
- remove eight trees as illustrated on the map provided
- replace sections of existing driveways reconstruct driveways, driveway crossovers, and associated kerb and channel
- construct concrete medians, cycle and pedestrian ramps.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including lane closures, minor traffic delays and reduced speed limits.

Project funded by Townsville City Council.
Date published: Thursday 21 August 2025
Work boundaries: Murray Street, between Gregory and Stokes Streets, North Ward.
Estimated start: November 2025
Expected duration: Seven (7) months
Normal work hours: 6am to 6pm Monday to Saturday.
Update (21 August 2025):
Council will commence utility upgrades along Murray Street from Tuesday 2 September 2025, beginning with the sewer main near the intersection with Gregory Street, North Ward. Works will take place within the drainage easement adjacent to the new Murray Street culvert and will not impact on regular traffic flow. This is expected to take six (6) weeks to complete.
With culvert works now complete, Townsville City Council still plans to undertake roadworks and utility service upgrades along Murray Street, between Gregory and Stokes Streets, North Ward.
However, in the interest of safety, this stage of the project is on pause as Council prioritises slope remediation works along Stanley Street and Castle Hill Road before the next wet season.
Preliminary works will commence from November 2025. Construction crews may not be on-site full-time while we undertake preliminary works.
Roadworks are anticipated to commence from March 2026. Works are expected to take three (3) months to complete, weather permitting.
We will provide you with more information regarding these emergent works soon.
As part of this project, Council will:
- repair and replace the top layer of the road surface to improve its condition and extend its lifespan
- renew and replace existing water and wastewater pipes to improve infrastructure and prevent service disruptions.
If you live in or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including lane closures, minor traffic delays and reduced speed limits.
This project is proudly funded by the Queensland Government’s Works for Queensland Program.
Date published: Monday 15 September 2025
Work boundaries: No Name Road south to Bidwilli Road.
Estimated start: Thursday 17 September 2025
Expected duration: Seven (7) months
Normal work hours: 6am to 6pm Monday to Saturday.
Council will be carrying out work to extend No Name Road south to Bidwilli Road. The project includes upgrading the Ghost Gum Road and Bidwilli Road intersections to connect with No Name Road, and creating new northern access from DriveIt NQ along Ghost Gum Road to No Name Road.
These works form part of the enabling infrastructure for the Lansdown Eco‑Industrial Precinct and will be delivered by civil contractor BMD Constructions.
These works will include:
- Applying the final road seal to the existing section of No Name Road.
- Extending pavement from the existing section of No Name Road south to Bidwilli Road.
- Constructing new road pavement from DriveIt NQ along Ghost Gum Road to No Name Road.
- Upgrading the No Name Road / Ghost Gum Road and No Name Road / Bidwilli Road intersections.
- Installing new culverts and drainage structures to improve stormwater flow.
- Providing flag lighting at intersections, along with line marking, signage, and fencing.
If you live in or are travelling through the area, you may experience:
- Construction machinery and vehicle movement.
- Increased levels of dust, noise, and vibrations.
- Temporary traffic changes, including lane closures, temporary traffic lights, minor traffic delays and reduced speed limits.
Lansdown Eco-Industrial Precinct is Jointly funded by the Australian Government and Queensland Government, in association with Townsville City Council.
Date published: Monday 1 December 2025
Work boundaries: Saunders Beach Road, between the street boundaries of The Bruce Highway and Reef Street in Saunders Beach
Estimated start: Monday 8 December 2025
Expected duration: Two (2) months
Normal work hours: From 6am to 6pm Monday to Saturday
What works are coming up?
Council is undertaking roadworks on Saunders Beach Road, between the street boundaries of The Bruce Highway and Reef Street in Saunders Beach. The works include the installation of road verge speed warning signage and road improvements designed to enhance road safety.
This project forms part of Council’s annual Roadworks program, which aims to maintain or improve our Council controlled road network. The program ensures our community’s connectivity needs are met and continues to support the growth of our region.
What will the works include?
- installation of designated road informational and directional signage including minor roadworks
- painting road markings and installation of reflective markers or signage.
What does this mean for me?
If you live near or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary traffic changes, including minor traffic delays and reduced speed limits.
Funding
This project is proudly funded by the Australian Government Blackspot program – an Australian Government road safety initiative, that aims to improve road safety and delivered in partnership with Townsville City Council.

Water Mains
Date published: Wednesday 15 October 2025
Work boundaries: Hamilton Tank Reservoir, Castle Hill
Estimated start: Mid-November 2025
Expected duration: Three (3) months
Normal work hours: 6am to 6pm Monday to Saturday
Council is now in the final stages of planning the delivery of the Hamilton Tank Reservoir renewal, including associated infrastructure
works next to the Goat Track adjacent to Hillside Crescent in Castle Hill.
This initiative reflects Council’s commitment to investing $352 million this year to enhance roads, transport infrastructure, parks, and
water systems – ensuring that all properties continue to receive efficient and reliable water services.
As part of this project, Council will:
- install a temporary water tank to maintain water supply
- remove and replace the existing reservoir tank with a new fit-for purpose tank
- upgrade access ladders, supports, pipework, and remote monitoring systems.
If you live nearby or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
- temporary, short-term closure of the walking track adjacent to the work zone
- water outages may occur during the works. Council will notify affected properties in advance to reduce any inconvenience.
Project proudly funded by the Queensland Government’s Works for Queensland program and delivered in partnership with Townsville City Council.

Date published: Tuesday 11 November 2025
Work boundaries: Mount Low Reservoir, Bushland Beach
Estimated start: Tuesday 18 November 2025
Expected duration: Six (6) months
Normal work hours: From 6am to 6pm Monday to Saturday
Council is undertaking construction works to deliver the renewal of Water Tank 1 at the Mount Low Reservoir, located at Euskadi Court in Bushland Beach.
This initiative reflects Council’s commitment to investing $352 million this year to enhance roads, transport infrastructure, parks, and water systems – ensuring that all properties continue to receive efficient and reliable water service.
As part of this project, Council will:
- renovate the reservoir roof.
- install access ladders and platforms.
- replace pipework.
- reinstate corrosion protection.
- apply a new internal protective coating to the tank.
If you live near or are travelling through the area, you may experience:
- construction machinery and vehicle movement
- increased levels of dust, noise, and vibrations
Council advises that renewal works affect Water Tank 1 only. Water Tank 2 will remain operational and continue servicing residents.
Project proudly funded by the Queensland Government’s Works for Queensland program and delivered in partnership with Townsville City Council.

Recently Completed
| Location | Works | Description |
|---|---|---|
| Winifred Street, Mundingburra | Stormwater Drainage Upgrade | Preliminary preloading works completed. |
| North Street, West End | Roadworks | Roadworks completed |
| Jones Road, Woodstock | Roadworks | Completed roadworks. |
| Charles Street and Lindeman Avenue, Cranbrook | Roadworks | Roadworks completed |
| King Street and Flinders Street, Townsville City | Roadworks | Roadworks completed |
| Townsville Recreational Boating Park, Fifth Avenue, Railway Estate | Ross River Erosion Remediation Works | Erosion Remediation Works Completed |
| Suburban Catchment Area, Kirwan | Tree Maintenance | Completed tree maintenance. |
| Denham Street, Townsville City | Roadworks | Completed roadworks. |
| York Court, Horseshoe Bay | Roadworks | Roadworks completed |
| Sooning Street, Nelly Bay | Blackspot Roadworks | Roadworks completed |
| Lakeside Drive, Idalia | Fencing Reinstatement Works | Fencing Reinstatement Works Completed |
| Stanley Street, Townsville City | Slope Remediation | Completed rockfall protection and slope stabilisation. |
| Riverside Green, Douglas | Riverside Green Open Space Renewal – Stage 2A | New junior themed play area delivered. |
| The Green, Iris Lane, Burdell | Fence Replacement | Fence replaced |
| Flinders Street, Townsville City | Roundabout Sign Reinstatement | Roundabout Sign Reinstated |
| Yarrawonga Reservoir, Castle Hill Road, Castle Hill | Temporary Tank Installation | Temporary Tank Installed |
| Ewen Jones Bridge, Ingham Road, Garbutt | Guard Rail Reflectors Reinstatement | Guard Rail Reflectors Reinstatement Completed |
| 55 Merivale Street, Jensen | Drainage Works | Drainage Improvement Works completed |
| Geoffrey Bay, Arcadia | Coastal Drone Survey | Coastal Drone Survey conducted |
| Locations throughout West End, South Townsville, Railway Estate, Oonoonba, and Idalia., Various | Sewer Maintenance Hole and Wastewater Pipeline Renewal | Sewer Maintenance Hole and Wastewater Pipeline Renewal |


